Spirebush

BSPSPT132 kV

At a glance

Generation headroom, free

Not published

Other figures

Sources retrieved 31 Oct 2026
Demand headroom
Not published
Fault level
Not published
Not openly published by NESO
Firm capacity
Not published

Location

55.54602, -4.07014

From DNO data
Directions (Google Maps, new tab)

Connection queue

NESO TEC Register (live, archive datastore dump), retrieved 31 Oct 2026

Queued
400 MW
Connected
0.0 MW
Projects
1
See the 1 project behind this queue with Pro

Voltage levels

  • 132 kVSpirebush SPTNot openly published by NESO

Data source

Transmission owner: Scottish Power Transmission. Licence: CC BY 4.0

Derived from publicly available DNO and TSO datasets: we cluster, merge and calculate from the published records, so these figures are modified from the source. Indicative only; verify directly with the operators before making connection decisions. Attribution and licences